Phase II Construction PDF Print E-mail

Southwest Chinese Baptist Church (SWCBC)

12525 Sugar Ridge Blvd., Stafford, Texas 77477
(281) 495-1511

 


The Creation of Phase II Church Building

 

  • Construction contract signing, (02/29/2004)
  • Ground breaking, (02/29/2004)
  • Construction begin, (03/06 - 03/14/2004)
  • Church bond sale, (03/13 - 03/20/2004)
001_sign_1 001_sign_2 001_sign_3 002_grdbrk_1 002_grdbrk_2 002_grdbrk_3 003_constr_01 003_constr_02 003_constr_03 004_bond_1 004_bond_2

 

  • Drainage / Piers / Plumbing / Slab Preparation, (3/22/2004)
  • Pour concrete slab, (3/30/2004)
  • Grease trap & drainage / slab, (04/02/2004)
  • Steel Columns for partitions, (04/05/2004)
  • Pour tilt wall concrete, (04/29/2004)
constr_04 constr_05 constr_06 constr_07 constr_08 constr_09 constr_10 constr_11-0 constr_11-1 constr_12 constr_13 constr_14 constr_15 constr_16 constr_17 constr_18 constr_19 constr_20 constr_21 constr_22 constr_23 constr_24 constr_25-0 constr_25-1 constr_25-2 constr_25-3

 

  • Tilt walls installation, (05/02/2004)
  • Parking lot /Side walk / Steel work, (05/20/2004)
  • Roof work, (05/20/2004)
  • Roof insulation installation, (05/28/2004)
  • Roof work done, (6/3/2004)
  • Plumbing / AC / Electrical / Partitions, (06/03 - 06/13/2004)
  • Main Entrance Glass Doors, (6/13/2004)
constr_26 constr_27 constr_28 constr_29 constr_30 constr_31 constr_32-1 constr_32-2 constr_33 constr_34 constr_35-1 constr_35-2 constr_36 constr_37 constr_38-1 constr_38-2 constr_39 constr_40 constr_41 constr_42 constr_43 constr_44 constr_45 constr_46 constr_47

 